The Hub · 30 Freeman Farm Rd · Duncan, SC

Two charging platforms on one 2.5 MW site

Ten Tesla V4 Superchargers and six Espen dispensers share a single Duke Energy service. Four of the Tesla stalls are pull-through, and a 1.26-acre outparcel sits at the entrance.

Tesla

V4 Supercharger

10 posts · up to 325 kW

  • 6 standard stalls
  • 4 pull-through stalls for trailers and larger vehicles
  • NACS connector
  • Serviced and maintained by Tesla

Espen

EVC/D360 dispenser

6 dispensers · up to 360 kW

  • CCS1 and NACS cables on every dispenser
  • Fed by two 360 kW Espen power cabinets
  • Open to every EV brand

Site layout

Two parcels, one destination

The hub parcel holds the chargers, ADA spaces and the utility yard. The outparcel beside it is held for a retail or food tenant.

Hub parcelLot 1-C-2 · 0.93 ac
OutparcelLot 1-C-3 · ±1.26 ac
Parking18 spaces: 12 standard, 4 pull-through, 2 ADA van-accessible
AccessFreeman Farm Rd, ≈400 ft west of SC-101
Duncan hub site layout (schematic) Two parcels on Freeman Farm Road. The 0.93-acre hub parcel holds 6 standard Tesla stalls, 4 pull-through Tesla stalls, 6 Espen stalls, 2 ADA spaces and the utility yard. The 1.26-acre outparcel sits beside it. Outparcel Lot 1-C-3 · ±1.26 ac build-to-suit / ground lease HUB PARCEL · LOT 1-C-2 · 0.93 AC Tesla V4 · 6 standard UTILITY YARD Tesla V4 · 4 pull-through ADA Espen · 6 FREEMAN FARM RD → SC-101 (≈400 ft) → I-85 EXIT 60
Tesla V4 Espen ADA Outparcel
Schematic only, not to scale. Stall positions are illustrative.

Utility service

Enough power to run every stall at once

A dedicated Duke Energy transformer feeds the site, sized so all 16 ports can charge at the same time with room to add capacity later.

UtilityDuke Energy
Transformer2,500 kVA
Service480 V, 3-phase, 4-wire
Switchboard3,000 A
Engineer of recordMatrix Technologies · R70154

Location

I-85 Exit 60, between Atlanta and Charlotte

The hub sits on the Greenville–Spartanburg stretch of I-85, which carries about 103,900 vehicles a day past Exit 60.

Duncan on the I-85 corridor To scale: Atlanta to Duncan is about 165 miles; Duncan to Charlotte is about 85 miles. Atlanta Charlotte Exit 60 · Duncan ≈165 mi ≈85 mi 0 50 100 150 200 250 mi
Drawn to scale along I-85. Distances are approximate road miles.
  • BMW ManufacturingBMW's largest plant worldwide0.5 mi
  • GSP International AirportGreenville-Spartanburg1.2 mi
  • Inland Port GreerIntermodal rail and freight1.8 mi
  • Brockman AutomotiveNext doorAdjacent
  • Qualified Opportunity ZoneFederal designationInside